PICTURES: FOUNDATION WORK IN PROGRESS | |
|
|
|
November 30, 2012: Concrete being poured
December 3, 2012: The foundation is taking shape
December 3, 2012: Foundation wall
December 6, 2012: Preparing for the footings in the deeper section of the foundation
December 12, 2012: The forms are going in place for the walls in the partial basement area
December 20, 2012: A little snow on the ground but work continues on
January 7, 2013: Backfilling the foundation
January 18, 2013: It is -14°C with a windchill of -25°C and the work continues to progress | |
|
|
|
|
| |